Chapter 4 Architecture and Structural Design
4.1 Architectural Design
4.1.1 Design basic information
Teh factory needs to provide local meteorological data
4.1.2 Architectural Design
In order to save land, the raw material workshop, glaze workshop, glazing workshop, firing workshop, finished product inspection, finished product warehouse, etc. in this project are placed on the first floor of the production workshop. The molding workshop, plaster mold workshop and workshop office area are placed on the second floor of the production workshop. The third floor is the casting workshop for the Phase II project (600,000 pcs). Other auxiliary workshops, substations, gas stations, offices and other buildings, if they meet different requirements, shall adopt different seismic fortification, fire prevention and other standards according to their production categories and the current relevant national design specifications. Different building structures and building levels.
4.1.3 Structural Design
Design basis: according to your site geological survey report and natural conditions.
The construction area of the project is as follows
serial number | construction project name | unit | quantity | Remark |
1 | Raw material and glaze workshop | m2_ | 3160 | 1.2 million pcs |
2 | Casting workshop | m2 | 37292 | 1.2 million pcs |
3 | firing workshop | m2 | 5000 | 1.2 million pcs |
3 | Gypsum workshop | m2 | 2592 | 1.2 million pcs |
4 | Finished product warehouse | m2 | 8000 | 1.2 million pcs |
5 | Other workshops | m2 | 9005 | 1.2 million pcs |
total | m2 | 65049 |